Renewable Energy Project of the Year
Winner:
Prolectric Services
A417 Missing Link: Transforming How Major Infrastructure Projects can be Powered in the UK
Prolectric Services won edie’s Renewable Energy Project of the Year Award for its work on the A417 Missing Link scheme, where it proved that renewable temporary power and lighting can outperform diesel at scale on one of the UK’s most environmentally sensitive infrastructure projects.
The challenge
Gloucestershire’s A417 “Missing Link” is a critical three-mile, single-lane stretch of road between the Brockworth Bypass and Cowley Roundabout that has long been a significant bottleneck – causing congestion, diverting motorists onto unsuitable local roads and contributing to a high incidence of serious accidents. A large-scale road improvement scheme is underway to resolve these issues.
Set within the Cotswolds National Landscape, an Area of Outstanding Natural Beauty, the 40-hectare construction site demanded an approach that could maintain safe, reliable operations while reducing emissions, noise, fuel use and disruption to local communities and protected wildlife. Varying power loads and the need for dependable overnight operation added to the challenge.
The solution
Prolectric, Kier and National Highways developed a solar-first lighting and power strategy focused on trialling, validating and scaling renewable off-grid solutions across the site. Instead of conventional diesel generators and tower lights, more than 80 solar lighting, hybrid power and battery storage units were deployed.
Early adoption enabled Prolectric to attend site survey meetings before the project broke ground, allowing a tailored delivery programme to be developed with environmental performance embedded from the outset.
How the project works
Renewable lighting and hybrid power technologies were trialled in live construction conditions before being rolled out more widely across the site. This phased approach reduced risk and ensured operational reliability; early trials validated the technology quickly, enabling the team to scale confidently without disrupting programme delivery.
Live monitoring, adaptive charge modes and careful matching of hybrid systems to actual load requirements ensured reliable performance while minimising unnecessary fuel use. Remote monitoring also improved asset management and reduced the need for servicing and refuelling visits, lowering operational risk and vehicle movements.
The results
In the last year alone, Prolectric’s solutions have eliminated 833,689kg CO2e, avoided 270,574 litres of diesel and generated £638,180 in operational cost savings. Hybrid deployments achieved fuel reductions of more than 75%, while a single three-phase solar battery energy storage installation delivered peak savings of 400kg CO2e and more than £200 per day.
Solar lighting removed the need for trenching and mains connections, reducing site disturbance, while Dark Sky-approved lighting minimised light spill to help protect sensitive wildlife. Quieter hybrid and battery systems improved conditions for site staff and reduced noise for neighbouring communities. Gavin Jones, Project Director at Kier Transportation Major Projects, said: “The transition was seamless, delivering significant cost savings without compromising performance. These technologies are setting a new standard for powering major infrastructure projects.”
Kier, Prolectric and National Highways will continue to expand the use of hybrid and battery applications across the site, using performance data to optimise deployments and further displace diesel – creating a replicable blueprint for lower-carbon construction on future infrastructure projects.
At a glance
Who: Prolectric Services, with Kier and National Highways
What: Solar-first temporary lighting and power on the A417 Missing Link
Where: UK
Why: To replace diesel-dependent site lighting and power with cleaner, lower-impact alternatives
When: Ongoing since early 2023
Runners up
Alcatel Submarine Networks
Decarbonising the Power Supply with Onsite Generation
Alcatel Submarine Networks manufactures submarine telecoms cable at its Greenwich site, where planned production increases sat awkwardly against its decarbonisation commitments. It installed 2,694 solar panels, totalling 1,347kWp, on the large factory roof under a power purchase agreement with Electron Green, avoiding upfront capital and leaving maintenance and performance risk with the developer. Feasibility work covered roof structural integrity and grid connection, and installation was coordinated around a 24-hour manufacturing operation. Construction ran from October 2025 to March 2026, with generation beginning in April. The system is forecast to supply 20% of annual site electricity and cut 165 tonnes of CO2.
AlphaESS UK, Immersa & Quest Power
Mobile CT & MR Scanners
Mobile CT and MRI units used for lung cancer screening have historically run on diesel generators, which must supply the stable voltage and rapid response that imaging equipment demands. AlphaESS UK, Immersa and Quest Power developed an off-grid battery system pairing AlphaESS TB125 units, each 125kW and 261kWh, with 300kVA static transfer switches, configured so the battery meets most daily load and the generator runs only to recharge and cover overnight operation. Following research and field trials, Quest Power committed to 18 systems totalling 3MW and 4.698MWh. Seven were operational by June 2026, with the remainder scheduled to follow.
Equans UK & Ireland
Babraham Road Park & Ride Smart Energy Grid
Equans has built a 2.5MWp solar carport at Cambridgeshire County Council's Babraham Road park and ride, combining 32 electric vehicle charge points and three accessible PAS-compliant points with a 2km private wire that supplies surplus renewable electricity directly to Cambridge University Hospitals. The carport was designed to add generation without losing parking capacity, and construction used hydrotreated vegetable oil in all site machinery, avoiding 109.7 tCO2e. Underground infrastructure and spare capacity were installed for future chargers, including planned bus charging. Over a 30-year life the scheme is expected to generate 65GWh and avoid more than 15,000 tonnes of CO2.
Mars & MG
Pringles Solar Park
Mars has installed a rooftop solar array on the 60,000 square metre warehouse serving its Pringles manufacturing plant at Mechelen in Belgium. The array comprises 13,000 panels with a peak capacity of 8,000kWp. Because the warehouse sits on the opposite side of a railway line from the factory, the electricity is carried to the plant through an underground cable, an arrangement the company describes as unusual at this scale and one which required governmental approvals relating to the railway. Total generation is around 7GWh a year, meeting around 15% of the plant's annual electricity requirement.
Protium Green Solutions
Protium, Pioneer 2, Green Hydrogen Facility
Pioneer 2 is Protium's green hydrogen facility in South Wales, built around a modular, containerised 2.5MW PEM electrolyser system designed to produce up to one tonne of hydrogen a day, 25 times the output of the company's first plant. The rationale is that demand from heavy transport, logistics, industry and off-grid users exists but supply constrains it. The facility is intended to serve the M4 corridor, South Wales and South West England, and provides grid flexibility through variable operation. Construction was powered by hydrogen fuel cells and batteries rather than diesel generators, on the site of a former car park.
RAW Charging
Landsec: 1000 EV Bays Powered by Renewable Energy
RAW Charging is converting underused parking at 28 Landsec retail and leisure destinations into electric vehicle charging under a £24.5m, 20-year agreement covering 1,000 bays. Charger speeds are matched to how long visitors actually stay, and legacy units are replaced rather than supplemented. Every charger sits on a new grid connection supplied with renewable electricity, and all bays connect to the ChargePoint network, with contactless payment and broad app compatibility. More than 150 bays are live across five sites, including Cardigan Fields in Leeds and Parrs Wood in south Manchester, with the first hub live eight days after the partnership was announced.
SolarSense & Freedom Leisure
Clean Energy Scheme
Freedom Leisure's annual energy costs rose from £8m to £22m during the energy crisis, threatening services at facilities receiving more than 23 million visits a year. Working with SolarSense, local authorities and public funding bodies including Sport England and Sport Wales, the leisure trust installed 1.56MWp of solar across ten sites in England and Wales, comprising 3,451 panels, alongside 156kWh of battery storage and monitoring systems. Work was completed on time and budget without closing facilities. The £1.33m scheme is projected to generate 1.51GWh a year, cut 327 tonnes of CO2 annually and repay itself in around 3.5 years.
Tidal Pumping & Hyro
Hydro-electric Generation
This entry sets out a design proposal to use tidal flow into and out of ocean locks to pump fresh water into storage, which would then be released through conventional hydroelectric generation. This would provide constant baseline generation day and night, addressing the intermittency that affects other renewable technologies, and could therefore displace gas, oil and nuclear generation. The proposal also envisages shoreline generation sites supporting battery recharging for electric ferries around the UK, and industrial parks sited next to generation in order to reduce transmission losses and infrastructure requirements.